River Tyne (Tunnels) Order
Table of contents
- Decision Letter
- TRANSPORT AND WORKS ACT 1992
TOWN AND COUNTRY PLANNING ACT 1990
PROPOSED NEW TYNE CROSSING - Summary of the Inspector's recommendations
- Summary of the Secretary of State's decisions
- Post-inquiry representations and amendments to the application
- Secretary of State's consideration
- Overall need for the New Tunnel Crossing: its objectives and policy framework
- The main alternatives considered
- Compulsory acquisition powers
- Funding arrangements and tolling powers
- Effects on the local and regional economy
- Traffic impacts
- Effects on residents and businesses
- Environmental effects and mitigation measures
- Inspector's overall conclusions and recommendations
- The Secretary of State's overall conclusions
- Changes to the Order
- Planning direction and conditions
- Notice of determination
- Challenge to decisions
- Distribution
- Annex 1
- Time limits for reserved matter applications and for commencement of development
- Reason:
- Reason:
- Code of Construction Practice and related Environmental Management Plans
- Reason:
- Scheme of works for the River Tyne
- Reason:
- Time limits on dredging in the River Tyne
- Reason:
- Reserved matters (all phases)
- Reason:
- Specific matters - North Tyneside
- Reason:
- Reason:
- Protection of surface waters
- Reason:
- Protection of items of archaeological interest
- Reason:
- Protection of trees and shrubs
- Reason:
- Hours of working - general
- Reason:
- Hours of working - blasting
- Reason:
- Storage of dredged arisings
- Reason:
- Environmental protection - air quality
- Reason:
- Landscaping
- Reason:
- Remediation validation
- Reason:
- Annex 2
- Right to challenge orders made under the TWA
- CHALLENGES TO DEEMED PLANNING PERMISSION GIVEN IN CONNECTION WITH A TWA ORDER